C2010-555 · Question #106

The supervisor has specified that the job plans be constructed so that the tasks on the work order will automatically start when the preceding task is complete. What function on a job plan makes…

The correct answer is D. Flow Control. See the full explanation below for the reasoning.

Question

The supervisor has specified that the job plans be constructed so that the tasks on the work order will automatically start when the preceding task is complete. What function on a job plan makes this possible?

Options

  • AWorkflow
  • BConditions
  • CRevisioning
  • DFlow Control

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    11% (2)
  • C
    5% (1)
  • D
    79% (15)