IBM
C2010-530 · Question #79
A company wishes to change the logic within a Workflow process but users currently have records within the process. Which would be the correct method to achieve this?
The correct answer is A. Create a process revision, validate, enable and activate it. See the full explanation below for the reasoning.
Question
A company wishes to change the logic within a Workflow process but users currently have records within the process. Which would be the correct method to achieve this?
Options
- ACreate a process revision, validate, enable and activate it.
- BSuspend the Workflow process, make the required changes and activate it.
- CDisable and Deactivate the Workflow, make the required changes and activate it.
- DUpdate the workflow process logic and perform an Admin Mode Database Configuration.
How the community answered
(54 responses)- A74% (40)
- B4% (2)
- C15% (8)
- D7% (4)
Community Discussion
No community discussion yet for this question.