A company has a large number of complex BIRT reports accessed by many users. An administrator wants to configure automatic cancellation of very large reports from processing once a configurable…
The correct answer is B. Report Server Limits. See the full explanation below for the reasoning.
Question
A company has a large number of complex BIRT reports accessed by many users. An administrator wants to configure automatic cancellation of very large reports from processing once a configurable limit has been reached. Which feature can be used to configure this?
Options
- AReport User Limits
- BReport Server Limits
- CReport Limit Cron Task
- DReport Schedule Limits
How the community answered
(48 responses)- A6% (3)
- B81% (39)
- C2% (1)
- D10% (5)