What are two considerations when planning for an active data pool?

The correct answer is B. Number of versions of data to keep. E. Usage of LAN-free techniques for the active data pool. See the full explanation below for the reasoning.

Question

What are two considerations when planning for an active data pool?

Options

  • ARetention period for the data.
  • BNumber of versions of data to keep.
  • CUsage of dedup for the active data pool.
  • DUsage for fast restore or disaster recovery.
  • EUsage of LAN-free techniques for the active data pool.

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    74% (23)
  • C
    6% (2)
  • D
    13% (4)