What does the preschedulecmd option accommodate?

The correct answer is D. It executes an operating system command before the scheduled action. The preschedulecmd option specifies a command that the client program processes before it runs a schedule. The client program waits for the command to complete before it starts the schedule.

Administration and Operations

Question

What does the preschedulecmd option accommodate?

Options

  • AIt enables deduplication on the client.
  • BIt tests out a schedule prior to running.
  • CIt gives this schedule higher priority over other schedules.
  • DIt executes an operating system command before the scheduled action.

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    4% (1)
  • C
    13% (3)
  • D
    74% (17)

Explanation

The preschedulecmd option specifies a command that the client program processes before it runs a schedule. The client program waits for the command to complete before it starts the schedule.

Topics

#preschedulecmd#scheduler options#TSM client options#pre-schedule command