nerdexam
IBM

C2010-509 · Question #63

Which task or process might be included in a server administrative schedule?

The correct answer is D. Expire inventory. See the full explanation below for the reasoning.

Question

Which task or process might be included in a server administrative schedule?

Options

  • AShred disk
  • BPromote disk
  • CIngest inventory
  • DExpire inventory

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    8% (3)
  • C
    16% (6)
  • D
    71% (27)

Community Discussion

No community discussion yet for this question.

Full C2010-509 Practice