A software installation task has been developed which requires the target endpoint to be restarted upon action completion. The administrator is required to notify the end users of the pending reboot…

The correct answer is A. Offer. ger_Console_Operators_Guide.pdf(page 115)

Administration

Question

A software installation task has been developed which requires the target endpoint to be restarted upon action completion. The administrator is required to notify the end users of the pending reboot and provide the opportunity to delay the reboot for four hours. Which Take Action tab accomplishes this?

Options

  • AOffer
  • BExecution
  • CMessages
  • DPost Action

How the community answered

(18 responses)
  • A
    83% (15)
  • B
    6% (1)
  • D
    11% (2)

Explanation

ger_Console_Operators_Guide.pdf(page 115)

Topics

#software deployment#take action#reboot notification#offer tab