A task has been developed which upgrades the corporate VPN client to the latest version. The administrator is required to Take Action on this task while giving end users the option of whether or not…

The correct answer is B. Messages tab of the Take Action dialog. Android uses "sticky notifications" for messaging the end user. The notification will stay in the Android status bar until a user opens and dismisses the notification (which is the typical way that Android notifications work). The messages for Android are controlled by…

Software Distribution

Question

A task has been developed which upgrades the corporate VPN client to the latest version. The administrator is required to Take Action on this task while giving end users the option of whether or not they would like to install this version. How is this accomplished?

Options

  • AOffer tab of the Take Action dialog
  • BMessages tab of the Take Action dialog
  • CPre-Action tab of the Take Action dialog
  • DNotification tab of the Take Action dialog

How the community answered

(65 responses)
  • A
    6% (4)
  • B
    82% (53)
  • C
    2% (1)
  • D
    11% (7)

Explanation

Android uses "sticky notifications" for messaging the end user. The notification will stay in the Android status bar until a user opens and dismisses the notification (which is the typical way that Android notifications work). The messages for Android are controlled by "Messages" tab in the "Take Action Dialog", which is similar to any other BigFix nager/page/Sending+Messages+to+Mobile+Devices

Topics

#Take Action dialog#Messages tab#user notification#software deployment