IBM
C2010-508 · Question #41
C2010-508 Question #41: Real Exam Question with Answer & Explanation
The correct answer is C. Use the Software Deployment wizard to specify the baseline and select the updates.. See the full explanation below for the reasoning.
Question
A non-master operator has rights to create custom content. His manager wants him to create a baseline to deploy updates to Adobe Reader and Oracle Java. How can this be done?
Options
- ABaselines may not be used for application updates.
- BRight-click on the required update and select Add to New Baseline.
- CUse the Software Deployment wizard to specify the baseline and select the updates.
- DUse the Fixlet Debugger to compute the shal and size value. Manually create a baseline action
Community Discussion
No community discussion yet for this question.