IBM
C2010-508 · Question #31
Which tab within the Deployed Action window provides the overall current result status after an action is taken on a Fixlet?
The correct answer is C. Summary. See the full explanation below for the reasoning.
Question
Which tab within the Deployed Action window provides the overall current result status after an action is taken on a Fixlet?
Options
- AStatus
- BTargets
- CSummary
- DComputers
How the community answered
(40 responses)- A13% (5)
- B3% (1)
- C80% (32)
- D5% (2)
Community Discussion
No community discussion yet for this question.