An administrator is required to take action on a Fixlet within a small maintenance window. What should be selected to permit the clients to download these components before the scheduled action time?

The correct answer is C. On the Execution tab of the Take Action dialog, check the Start Client Downloads Before. See the full explanation below for the reasoning.

Question

An administrator is required to take action on a Fixlet within a small maintenance window. What should be selected to permit the clients to download these components before the scheduled action time?

Options

  • AOn the Execution tab of the Take Action dialog, check the Stagger Download Time to Reduce
  • BOn the Applicability tab of the Take Action dialog, check the Stagger Download Time to Reduce
  • COn the Execution tab of the Take Action dialog, check the Start Client Downloads Before
  • DOn the Applicability tab of the Take Action dialog, check the Start Client Downloads Before

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    79% (22)
  • D
    7% (2)