An operator has an existing baseline that she needs to modify, and she has rights to create custom content. In the baseline she wants to modify, a number of updates have been superseded. How does…

The correct answer is C. Select the baseline to update, right-click on it. select Edit, and remove the updates in question by. See the full explanation below for the reasoning.

Question

An operator has an existing baseline that she needs to modify, and she has rights to create custom content. In the baseline she wants to modify, a number of updates have been superseded. How does she remove them?

Options

  • ARights to create custom content do not provide the rights to modify custom content.
  • BSelect the baseline to update, right-click on it. select Edit and click the Remove Superseded Fixlet
  • CSelect the baseline to update, right-click on it. select Edit, and remove the updates in question by
  • DContact the master operator because they are the only console operators with the correct

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    73% (19)
  • D
    8% (2)