C2010-508 · Question #10

C2010-508 Question #10: Real Exam Question with Answer & Explanation

Sign in or unlock C2010-508 to reveal the answer and full explanation for question #10. The question stem and answer options stay visible for context.

Question

An operator has an existing baseline that she needs to modify, and she has rights to create custom content. In the baseline she wants to modify, a number of updates have been superseded. How does she remove them?

Options

  • ARights to create custom content do not provide the rights to modify custom content.
  • BSelect the baseline to update, right-click on it. select Edit and click the Remove Superseded Fixlet
  • CSelect the baseline to update, right-click on it. select Edit, and remove the updates in question by
  • DContact the master operator because they are the only console operators with the correct