How can the configuration be verified after the installation and configuration of Hot Standby for Hub Tivoli Enterprise Monitoring Servers (TEMS)?
The correct answer is A. Stop the Primary Hub TEMS and allow the Secondary Hub to take over. Thenreconfigure the. See the full explanation below for the reasoning.
Question
How can the configuration be verified after the installation and configuration of Hot Standby for Hub Tivoli Enterprise Monitoring Servers (TEMS)?
Options
- AStop the Primary Hub TEMS and allow the Secondary Hub to take over. Thenreconfigure the
- BStop the Primary Hub TEMS and allow the Secondary Hub to take over.The Tivoli Enterprise
- CStop the Primary Hub TEMS and reconfigure the SecondaryHub to act as the Primary. Then
- DStop the Primary Hub TEMS and reconfigure the Secondary Hub to act as the Primary. The Tivoli
How the community answered
(31 responses)- A77% (24)
- B3% (1)
- C6% (2)
- D13% (4)