nerdexam
IBM

C2010-501 · Question #23

Regarding the Run Configuration Step screen - which option requires running taskrunner.bat?

The correct answer is D. copy files now, perform the configuration step later. See the full explanation below for the reasoning.

Question

Regarding the Run Configuration Step screen - which option requires running taskrunner.bat?

Options

  • Aconfigure SMTP host
  • Bdeploy application files manually later
  • Cdefer the update of the Maximo database
  • Dcopy files now, perform the configuration step later

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    4% (1)
  • C
    4% (1)
  • D
    83% (19)

Community Discussion

No community discussion yet for this question.

Full C2010-501 Practice