IBM
C1000-163 · Question #179
A QRadar deployment professional is asked to plan a hardware migration for an Event Processor in HA. Two new appliances are ready to be used, and they use the same IP addresses. Which approach can…
The correct answer is C. Remove HA on the EPs, migrate to the new primary, then add the new secondary back in. See the full explanation below for the reasoning.
Question
A QRadar deployment professional is asked to plan a hardware migration for an Event Processor in HA. Two new appliances are ready to be used, and they use the same IP addresses. Which approach can be used to migrate the systems?
Options
- AUse the QRadar config backup and restore process to transfer all configurations.
- BUse rsync to transfer the contents of the /store/postgres partition to the new system.
- CRemove HA on the EPs, migrate to the new primary, then add the new secondary back in.
- DEnsure both systems are built as appliance type 500 and add them into the deployment as
How the community answered
(50 responses)- A2% (1)
- B10% (5)
- C84% (42)
- D4% (2)
Community Discussion
No community discussion yet for this question.