What are the metrics describing GDPS Continuous Availability?

The correct answer is A. Two or more active data centers in extended distance, RPO<1m and RTO<1m. Option A is correct because GDPS Continuous Availability is designed for extended-distance configurations with two or more active sites, delivering near-zero recovery objectives - RPO and RTO both under one minute - enabling workloads to survive a site failure with minimal…

Performance and Scalability

Question

What are the metrics describing GDPS Continuous Availability?

Options

  • ATwo or more active data centers in extended distance, RPO<1m and RTO<1m
  • BTwo active data centers in extended distance, RPO>1m and RTO>1h
  • CTwo data centers in metropolitan distance, RPO=0 and RTO=0
  • DSingle data center, RPO=0

How the community answered

(30 responses)
  • A
    93% (28)
  • B
    3% (1)
  • D
    3% (1)

Explanation

Option A is correct because GDPS Continuous Availability is designed for extended-distance configurations with two or more active sites, delivering near-zero recovery objectives - RPO and RTO both under one minute - enabling workloads to survive a site failure with minimal disruption.

Why the distractors fail:

  • B is wrong on the recovery metrics: RTO>1h is disaster recovery territory, not continuous availability, and RPO>1m reflects asynchronous replication (like Global Mirror), not CA.
  • C describes GDPS Metro Mirror - synchronous replication achieves RPO=0 and RTO=0, but only across metropolitan distances, not extended distance.
  • D is simply a single data center with no geographic redundancy, which is the opposite of what any GDPS solution provides.

Memory tip: Think of "Continuous Availability" as almost perfect but not quite - unlike synchronous Metro Mirror which hits the absolute zero mark, CA uses asynchronous-style stretched clustering over longer distances, so you get sub-minute (< 1m) rather than zero for both RPO and RTO. The phrase "CA = Close but not zero, at a Distance" can help you distinguish it from Metro Mirror's perfect zeros.