BPM-001 · Question #51
The diamond symbol in flowchart process mapping means
The correct answer is A. A decision is to be made. In standard flowchart notation, the diamond shape represents a decision point - a yes/no or true/false question that branches the process into two or more paths, making option A correct. Option B (another step) is wrong because process steps use rectangles, not diamonds. Option…
Question
The diamond symbol in flowchart process mapping means
Options
- AA decision is to be made
- BAnother step in the process
- CIndicates direction
- DIndicates the start of the process
How the community answered
(36 responses)- A92% (33)
- B3% (1)
- D6% (2)
Explanation
In standard flowchart notation, the diamond shape represents a decision point - a yes/no or true/false question that branches the process into two or more paths, making option A correct. Option B (another step) is wrong because process steps use rectangles, not diamonds. Option C (indicates direction) is wrong because direction is shown by arrows connecting shapes. Option D (start of process) is wrong because the start/end of a process uses an oval or rounded rectangle (called a terminal symbol).
Memory tip: Think of a diamond as a "fork in the road" - just like a road diamond warning sign makes you choose which way to go, the flowchart diamond makes you choose which path to follow based on a decision.