BPM-001 · Question #39
A swimlane process map:
The correct answer is A. Distinguishes the responsibilities for steps within a process. A swimlane process map gets its name from the horizontal or vertical "lanes" assigned to different actors, departments, or roles - each lane shows which party is responsible for which steps, making accountability and handoffs visually clear. This is exactly what option A…
Question
A swimlane process map:
Options
- ADistinguishes the responsibilities for steps within a process
- BUses colored visual indicators to indicate progress
- CLists tasks and deadlines
- DProvides real-time data on process efficiency
How the community answered
(51 responses)- A86% (44)
- B2% (1)
- C4% (2)
- D8% (4)
Explanation
A swimlane process map gets its name from the horizontal or vertical "lanes" assigned to different actors, departments, or roles - each lane shows which party is responsible for which steps, making accountability and handoffs visually clear. This is exactly what option A describes: distinguishing responsibilities for steps within a process.
Why the distractors are wrong:
- B - Swimlanes use spatial separation (lanes), not color indicators, to convey information; color-coding is a separate technique.
- C - Listing tasks with deadlines describes a Gantt chart or task list, not a swimlane map.
- D - Real-time efficiency data comes from dashboards or process monitoring tools, not a static process map.
Memory tip: Think of an actual swimming pool - each swimmer stays in their own lane. In a swimlane diagram, each "swimmer" (person or team) stays in their lane, making it immediately obvious who owns each step.