What are subsequent changes subject to once a requirements document has been signed off?

The correct answer is D. Requirements management. See the full explanation below for the reasoning.

Question

What are subsequent changes subject to once a requirements document has been signed off?

Options

  • ARequirements verification.
  • BRequirements documentation.
  • CRequirements validation.
  • DRequirements management.

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    7% (2)
  • C
    14% (4)
  • D
    76% (22)