BCS-ISEB
BH0-013 · Question #21
A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid. Which of the following would be an appropriate way of managing this…
The correct answer is B. Watch. See the full explanation below for the reasoning.
Question
A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid. Which of the following would be an appropriate way of managing this stakeholder?
Options
- AIgnore.
- BWatch.
- CKeep on side.
- DKeep informed.
How the community answered
(31 responses)- A6% (2)
- B81% (25)
- C10% (3)
- D3% (1)
Community Discussion
No community discussion yet for this question.