BH0-013 · Question #107

A stakeholder has been classified as 'some' on both the power/influence and interest axes of a power/interest grid. Which of the following would be an appropriate way of managing this stakeholder?

The correct answer is A. Keep on side. See the full explanation below for the reasoning.

Question

A stakeholder has been classified as 'some' on both the power/influence and interest axes of a power/interest grid. Which of the following would be an appropriate way of managing this stakeholder?

Options

  • AKeep on side.
  • BKeep watching.
  • CKeep informed.
  • DKeep satisfied.

How the community answered

(32 responses)
  • A
    69% (22)
  • B
    9% (3)
  • C
    3% (1)
  • D
    19% (6)

Community Discussion

No community discussion yet for this question.