A new system is about to be developed. Which of the following functions has the highest level of risk?

The correct answer is A. Likelihood of failure = 20%; impact value = ?00,000. In (B) the product of probability ?impact has the value ?5,000; in (C) the value is ?,000 and in (D) it is ?,000. The value of ?0,000 in (A) is therefore the highest.

Test management

Question

A new system is about to be developed. Which of the following functions has the highest level of risk?

Options

  • ALikelihood of failure = 20%; impact value = ?00,000
  • BLikelihood of failure = 10%; impact value = ?50,000
  • CLikelihood of failure = 1%; impact value = ?00,000
  • DLikelihood of failure = 2%; impact value = ?00,000

How the community answered

(23 responses)
  • A
    83% (19)
  • B
    4% (1)
  • C
    9% (2)
  • D
    4% (1)

Explanation

In (B) the product of probability ?impact has the value ?5,000; in (C) the value is ?,000 and in (D) it is ?,000. The value of ?0,000 in (A) is therefore the highest.