Which of the following is NOT an aim of the Change Management process?

The correct answer is A. To deliver and manage IT services at agreed levels to business users. See the full explanation below for the reasoning.

Question

Which of the following is NOT an aim of the Change Management process?

Options

  • ATo deliver and manage IT services at agreed levels to business users
  • BThe impact of changes are better understood
  • CStandardized methods and procedures are used for efficient and prompt handling of all Changes
  • DAll changes to Service Assets and Configuration Items (CIs) are recorded in the Configuration

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    7% (2)
  • C
    14% (4)
  • D
    4% (1)