IT operations management have been asked by a customer to carry out non-standard activity that will cause them to miss an agreed service level target. How should they respond?

The correct answer is C. make a decision based on balancing stability and responsiveness. See the full explanation below for the reasoning.

Question

IT operations management have been asked by a customer to carry out non-standard activity that will cause them to miss an agreed service level target. How should they respond?

Options

  • Athey should escalate this decision to service strategy
  • Baccept the request as they must support customer business outcomes
  • Cmake a decision based on balancing stability and responsiveness
  • Drefuse the request because they must operate the service to meet the agreed service levels

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    13% (2)
  • C
    75% (12)
  • D
    6% (1)