Which of the following activities are responsibilities of a Supplier Manager? 1. Negotiating and agreeing Contracts 2. Updating the Supplier and Contract database 3. Planning for possible closure…

The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.

Question

Which of the following activities are responsibilities of a Supplier Manager? 1. Negotiating and agreeing Contracts 2. Updating the Supplier and Contract database 3. Planning for possible closure, renewal or extension of contracts 4. Managing relationships with internal suppliers

Options

  • A1, 2 and 3 only
  • B1, 3 and 4 only
  • C2, 3 and 4 only
  • DNone of the above

How the community answered

(36 responses)
  • A
    78% (28)
  • B
    14% (5)
  • C
    6% (2)
  • D
    3% (1)