Which of these would fall outside the scope of a typical service Change Management process?
The correct answer is D. A change to a business process that depends on IT Services. See the full explanation below for the reasoning.
Question
Which of these would fall outside the scope of a typical service Change Management process?
Options
- AA change to a contract with a supplier
- BA firmware upgrade to a server that is only used for IT Service Continuity purposes
- CAn urgent need to replace a CPU to restore a service during an incident
- DA change to a business process that depends on IT Services
How the community answered
(49 responses)- A6% (3)
- B16% (8)
- C4% (2)
- D73% (36)