Which of the following activities may, exceptionally, be omitted for an urgent change: 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a…
The correct answer is C. 2 and 3. See the full explanation below for the reasoning.
Question
Which of the following activities may, exceptionally, be omitted for an urgent change: 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a back-out plan
Options
- AAll of them
- B2 and 4
- C2 and 3
- D3 and 4
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C71% (20)
- D18% (5)
Community Discussion