BCS-ISEB
BH0-006 · Question #248
What type of improvement should be achieved by using the Deming Cycle?
The correct answer is B. Steady, ongoing improvement. See the full explanation below for the reasoning.
Question
What type of improvement should be achieved by using the Deming Cycle?
Options
- ARapid, one-off improvement
- BSteady, ongoing improvement
- CQuick wins
- DReturn on investment within 12 months
How the community answered
(53 responses)- A6% (3)
- B75% (40)
- C4% (2)
- D15% (8)
Community Discussion