BCS-ISEB
BH0-006 · Question #196
A change process model should include: 1. The steps that should be taken to handle the change with any dependences or co-processing defined, including handling issues and unexpected events 2…
The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.
Question
A change process model should include: 1. The steps that should be taken to handle the change with any dependences or co-processing defined, including handling issues and unexpected events 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures
Options
- A1, 2 and 3 only
- BAll of the above
- C1 and 2 only
- D1, 2 and 4 only
How the community answered
(54 responses)- A78% (42)
- B11% (6)
- C4% (2)
- D7% (4)
Community Discussion
No community discussion yet for this question.