BH0-006 · Question #196

A change process model should include: 1. The steps that should be taken to handle the change with any dependences or co-processing defined, including handling issues and unexpected events 2…

The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.

Question

A change process model should include: 1. The steps that should be taken to handle the change with any dependences or co-processing defined, including handling issues and unexpected events 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures

Options

  • A1, 2 and 3 only
  • BAll of the above
  • C1 and 2 only
  • D1, 2 and 4 only

How the community answered

(54 responses)
  • A
    78% (42)
  • B
    11% (6)
  • C
    4% (2)
  • D
    7% (4)