nerdexam
BCS-ISEB

BH0-006 · Question #184

A Service Design Package should be produced for which of the following? 1. A new IT service 2. A major change to an IT service 3. An Emergency Change to an IT service 4. An IT service retirement

The correct answer is D. 1, 2 and 4 only. See the full explanation below for the reasoning.

Question

A Service Design Package should be produced for which of the following? 1. A new IT service 2. A major change to an IT service 3. An Emergency Change to an IT service 4. An IT service retirement

Options

  • A1, 2 and 3 only
  • BAll of the other alternatives apply.
  • C1, 3 and 4 only
  • D1, 2 and 4 only

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    83% (25)

Community Discussion

No community discussion yet for this question.

Full BH0-006 Practice