BCS-ISEB
BH0-006 · Question #102
Which process is responsible for low risk, frequently occurring, low cost changes?
The correct answer is D. Request Fulfilment. See the full explanation below for the reasoning.
Question
Which process is responsible for low risk, frequently occurring, low cost changes?
Options
- ADemand Management
- BIncident Management
- CRelease and Deployment Management
- DRequest Fulfilment
How the community answered
(18 responses)- A6% (1)
- B6% (1)
- C11% (2)
- D78% (14)
Community Discussion
No community discussion yet for this question.