AZ-400 · Question #475
Drag and Drop Question You are implementing a new project in Azure DevOps. You need to assess the performance of the project. The solution must identify the following metrics: - How long it takes to c
The correct answer is Lead time; Defect escape rate. Lead time measures the total elapsed time from when a work item is created until it is completed and delivered, making it the correct KPI for 'how long it takes to complete a work item.' Defect escape rate specifically measures the percentage of defects that were not caught durin
Question
Exhibit
Answer Area
Drag items
Correct arrangement
- Lead time
- Defect escape rate
Explanation
Lead time measures the total elapsed time from when a work item is created until it is completed and delivered, making it the correct KPI for 'how long it takes to complete a work item.' Defect escape rate specifically measures the percentage of defects that were not caught during development and testing and instead made it to production, directly mapping to 'the percentage of defects found in production.' These two KPIs precisely match the described requirements.
Topics
Community Discussion
No community discussion yet for this question.