AZ-104 · Question #184
Your company has an Azure subscription that is used by multiple departments in your company. The subscription contains around 5 resource groups. Each department uses resources in several resource grou
The correct answer is C. Download the usage report D. Assign a tag to each resource E. From the Costs Analysis blade, filter the view by tag. Option A is incorrect since here the resources are used across various departments and are not constrained via resource groups. Option B is incorrect since the costing on a tag basis needs to be seen from Cost Analysis. https://docs.microsoft.com/en-us/azure/azure-resource-manage
Question
Exhibit
Options
- AAssign a tag to each resource group
- BUse the Resource costs blade of each resource group
- CDownload the usage report
- DAssign a tag to each resource
- EFrom the Costs Analysis blade, filter the view by tag
How the community answered
(60 responses)- A15% (9)
- B10% (6)
- C75% (45)
Explanation
Option A is incorrect since here the resources are used across various departments and are not constrained via resource groups. Option B is incorrect since the costing on a tag basis needs to be seen from Cost Analysis. https://docs.microsoft.com/en-us/azure/azure-resource-manager/resource-group-using-tags
Community Discussion
No community discussion yet for this question.