ASF · Question #32
In a Scrum project, when would a requirement get added to the Product backlog?
The correct answer is C. When the customer requests a new requirement. Option C is correct because the Product Backlog is a living list of everything the product might need, and new items are added whenever a stakeholder - most commonly the customer or Product Owner - identifies a new requirement or need. The backlog exists precisely to capture…
Question
In a Scrum project, when would a requirement get added to the Product backlog?
Options
- AWhen it is developed, but cannot yet be released.
- BWhen the team works on it for a particular release.
- CWhen the customer requests a new requirement.
How the community answered
(29 responses)- A7% (2)
- B3% (1)
- C90% (26)
Explanation
Option C is correct because the Product Backlog is a living list of everything the product might need, and new items are added whenever a stakeholder - most commonly the customer or Product Owner - identifies a new requirement or need. The backlog exists precisely to capture these requests at any point in the project, not just during sprints.
Option A is wrong because "developed but not yet released" describes an increment that is Done but not yet deployed - it has nothing to do with when items enter the backlog. Option B is wrong because working on a requirement during a sprint means it has already been selected from the backlog into the Sprint Backlog - it's too late in the process for the item to be "added" to the Product Backlog.
Memory tip: Think of the Product Backlog as a customer wish list - items go on the list the moment someone asks for them, not when you start shopping or after you've already bought something.
Topics
Community Discussion
No community discussion yet for this question.