AGILEPM-PRACTITIONER · Question #58

Several of the web developers working on the project have no Agile experience. When answering the questions in the Project Approach Questionnaire (PAQ), the Project Manager could not agree with the…

The correct answer is C. Organize a training workshop to brief all project-level and Solution. Option C is correct because DSDM requires that all project members genuinely understand and accept the approach before the project begins - training is the prescribed remedy when this criterion cannot be met, ensuring the team can work collaboratively within the framework. Why…

DSDM Practices and Governance

Question

Several of the web developers working on the project have no Agile experience. When answering the questions in the Project Approach Questionnaire (PAQ), the Project Manager could not agree with the statement 'all members of the project understand and accept the DSDM approach'. What action should the Project Manager take?

Options

  • AReplace the web developers with experienced Agile practitioners.
  • BAgree with the statement in the PAQ and keep a close watch on the web
  • COrganize a training workshop to brief all project-level and Solution
  • DAccept that the web developers are experts in their field and will be

How the community answered

(31 responses)
  • A
    26% (8)
  • B
    13% (4)
  • C
    55% (17)
  • D
    6% (2)

Explanation

Option C is correct because DSDM requires that all project members genuinely understand and accept the approach before the project begins - training is the prescribed remedy when this criterion cannot be met, ensuring the team can work collaboratively within the framework.

Why the distractors fail:

  • A is wrong because replacing competent developers is wasteful and disproportionate; DSDM favors empowering the existing team, not discarding domain expertise.
  • B is wrong because it involves falsifying the PAQ - agreeing to a statement you cannot honestly support undermines the entire purpose of the assessment and hides a real risk.
  • D is wrong because technical expertise does not substitute for DSDM knowledge; being a skilled developer is irrelevant if you don't understand or accept the Agile ways of working the team depends on.

Memory tip: In DSDM, the PAQ is a honesty check, not a rubber stamp - when a criterion fails, you fix the gap (train), you don't hide the gap (lie) or nuke the team (replace). Think: "Train before you complain to the PAQ."