Which 2 statements represent appropriate entries for the Prioritised Requirements List?

The correct answer is B. All correspondence sent to coffee shop owners by the new system should C. Further website developments to allow existing customers to access. Options B and C are correct because a Prioritised Requirements List (PRL) - a key DSDM/AgilePM artifact - captures what the solution/system must do: B describes a specific system behaviour (how correspondence should be handled), and C describes a system capability (website…

DSDM Products

Question

Which 2 statements represent appropriate entries for the Prioritised Requirements List?

Options

  • ACreation of a new coffee shop insurance product on the existing website
  • BAll correspondence sent to coffee shop owners by the new system should
  • CFurther website developments to allow existing customers to access
  • DThe Business Visionary will provide a formal acceptance of the coffee
  • EAn assessment will be made of the effectiveness of the techniques used

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    79% (22)
  • D
    4% (1)
  • E
    11% (3)

Explanation

Options B and C are correct because a Prioritised Requirements List (PRL) - a key DSDM/AgilePM artifact - captures what the solution/system must do: B describes a specific system behaviour (how correspondence should be handled), and C describes a system capability (website functionality for existing customers). Both are genuine, deliverable requirements that can be prioritised and built.

Why the distractors are wrong:

  • A describes the overall project objective or scope statement, not an individual prioritised requirement - it belongs in the Business Case or project definition, not the PRL.
  • D describes a project governance activity (Business Visionary sign-off/acceptance), which belongs in the project management plan or governance framework, not the requirements list.
  • E describes a post-project evaluation activity (technique effectiveness review), which belongs in the project review or lessons learned process.

Memory tip: Filter PRL candidates with the question "Does this describe something the system must DO or DELIVER?" - if it instead describes something a person must do (accept, assess, provide) or the project's overall goal, it doesn't belong in the PRL.