AGILEPM-PRACTITIONER · Question #50
During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent any Planning Authority issues.
The correct answer is A. Yes, because all stakeholders should attend the Daily Stand-up meetings. Option A is correct because in DSDM (AgilePM), the Daily Stand-up is open to all relevant stakeholders, and when a specialist such as the Local Planning Authority Officer is brought in as a temporary Specialist team member, they become part of the Solution Development Team for…
Question
During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent any Planning Authority issues.
Options
- AYes, because all stakeholders should attend the Daily Stand-up meetings.
- BYes, because each team member will have an opportunity to highlight any Planning Authority
- CNo, because NOT all members of the Solution Development Team will attend the Daily Stand-up.
- DNo, because only members of the Solution Development Team should be permitted to attend
How the community answered
(25 responses)- A96% (24)
- D4% (1)
Explanation
Option A is correct because in DSDM (AgilePM), the Daily Stand-up is open to all relevant stakeholders, and when a specialist such as the Local Planning Authority Officer is brought in as a temporary Specialist team member, they become part of the Solution Development Team for that Timebox and are expected to attend - ensuring planning concerns are surfaced daily.
Option B is incorrect not because the reasoning is entirely wrong, but because it is incomplete and does not capture the full principle; the better rationale is the broader stakeholder inclusion rule, not just the opportunity to highlight issues.
Option C is a distractor that misapplies a true fact (not all team members attend every stand-up) to reach a wrong conclusion - the question is about eligibility to attend, not mandatory 100% attendance by all members.
Option D is wrong because the LPA Officer is effectively a member of the Solution Development Team in this context, having been brought in as a temporary Specialist - so the restriction in D doesn't apply here.
Memory tip: Think "temporary = team member." Once someone is given a temporary Specialist role in a Timebox, they carry full team member rights, including Daily Stand-up attendance. If they're on the team, they're in the meeting.
Topics
Community Discussion
No community discussion yet for this question.