AGILEPM-PRACTITIONER · Question #38
Answer the following questions about the use of the Agile principles. Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have…
The correct answer is B. Never compromise quality. "Never compromise quality" (B) is correct because the scenario describes a deliberate decision to reject deliverables that fail the defined Must Have standards - quality gates are non-negotiable in Agile, and items not meeting them are explicitly marked as undelivered and…
Question
Answer the following questions about the use of the Agile principles. Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned. Which Agile principle MOST influences this course of action?
Options
- ACollaborate.
- BNever compromise quality.
- CBuild incrementally from firm foundations.
- DCommunicate continuously and clearly.
How the community answered
(34 responses)- A3% (1)
- B91% (31)
- C6% (2)
Explanation
"Never compromise quality" (B) is correct because the scenario describes a deliberate decision to reject deliverables that fail the defined Must Have standards - quality gates are non-negotiable in Agile, and items not meeting them are explicitly marked as undelivered and re-planned rather than accepted with defects.
Why the distractors are wrong:
- A (Collaborate) - Collaboration is about teamwork and stakeholder involvement, not the specific act of rejecting substandard work against defined criteria.
- C (Build incrementally from firm foundations) - This principle concerns iterative delivery and ensuring earlier work is solid before building on it; it doesn't directly drive the rejection of non-conforming items.
- D (Communicate continuously and clearly) - While communicating the failure is part of the process, the driving force behind the rejection decision is the quality standard itself, not the act of communicating.
Memory tip: Whenever a scenario involves rejecting, withholding acceptance, or re-planning work because it fails a defined standard, that's always a quality signal - the phrase "Must Have" is a direct reference to MoSCoW prioritisation, and failing a Must Have = a quality failure, pointing straight to B.