Which should always be the first step in the Continuous Change Management Cycle?

The correct answer is C. Discovery. Discovery: The Continuous Change Management Cycle starts with understanding the current situation, challenges, and opportunities. Discovery ensures that subsequent steps are informed

Agile Change Management Process

Question

Which should always be the first step in the Continuous Change Management Cycle?

Options

  • AIdeas.
  • BPrioritization.
  • CDiscovery.
  • DAction.

How the community answered

(58 responses)
  • A
    2% (1)
  • B
    5% (3)
  • C
    90% (52)
  • D
    3% (2)

Explanation

Discovery: The Continuous Change Management Cycle starts with understanding the current situation, challenges, and opportunities. Discovery ensures that subsequent steps are informed

Topics