Which plain defined by DSDM, has a planning horizon that includes the end of a project?

The correct answer is C. Delivery. The Delivery Plan defined by DSDM has a planning horizon that includes the end of the project. This plan looks towards the future, often months or years ahead, to guide the incremental delivery of the project's outcomes.

DSDM Products

Question

Which plain defined by DSDM, has a planning horizon that includes the end of a project?

Options

  • ATimebox
  • BDetailed
  • CDelivery
  • DHigh-Level

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    91% (20)
  • D
    5% (1)

Explanation

The Delivery Plan defined by DSDM has a planning horizon that includes the end of the project. This plan looks towards the future, often months or years ahead, to guide the incremental delivery of the project's outcomes.

Topics

#Delivery Plan#planning horizon#DSDM plans