An organization has decided to roll out the transition to a new software application, one department at a time. What type of delivery strategy is being adopted?
The correct answer is B. Phased. Phased Approach: Rolling out change one department at a time reflects a phased delivery strategy, which allows for controlled implementation and adjustment before wider deployment.
Agile Project Management Approach
Question
An organization has decided to roll out the transition to a new software application, one department at a time. What type of delivery strategy is being adopted?
Options
- ABig Bang.
- BPhased.
- CVoluntary Adoption.
- DMany small incremental/iterative releases.
How the community answered
(62 responses)- A2% (1)
- B92% (57)
- C2% (1)
- D5% (3)
Explanation
Phased Approach: Rolling out change one department at a time reflects a phased delivery strategy, which allows for controlled implementation and adjustment before wider deployment.
Topics
#delivery strategy#phased deployment#release planning