A group has a resource allocation maximum of 50% and the job maximum is set to 1. Two users within this resource group each execute 1 job at the same time, which statement is correct?
The correct answer is B. Each job gets 50% but only one job runs at a time. See the full explanation below for the reasoning.
Question
A group has a resource allocation maximum of 50% and the job maximum is set to 1. Two users within this resource group each execute 1 job at the same time, which statement is correct?
Options
- AEach job gets 25% and both run at the same time.
- BEach job gets 50% but only one job runs at a time.
- CEach job gets 50% and both run at the same time.
- DYou cannot set the job maximum per resource group.
How the community answered
(32 responses)- A3% (1)
- B84% (27)
- C9% (3)
- D3% (1)