Given the following BPML, what will the value of "c" be in ProcessData when the Business Process (BP) completes successfully?
The correct answer is D. 16. See the full explanation below for the reasoning.
Question
Given the following BPML, what will the value of "c" be in ProcessData when the Business Process (BP) completes successfully?
Options
- A10
- B11
- C15
- D16
How the community answered
(20 responses)- A5% (1)
- B15% (3)
- C5% (1)
- D75% (15)