IBM
A2060-218 · Question #7
In an FTP pull scenario with many trading partners, if the expected file is not available at the external FTP Server, the Business Process (BP) should reconnect and check for the file again after…
The correct answer is A. Wait service. See the full explanation below for the reasoning.
Question
In an FTP pull scenario with many trading partners, if the expected file is not available at the external FTP Server, the Business Process (BP) should reconnect and check for the file again after about 15 - 30 minutes. Which service would provide the optimal performance for the timing logic?
Options
- AWait service
- BSleep service
- CSchedule service
- DFTP Client Begin Adapter
How the community answered
(43 responses)- A77% (33)
- B2% (1)
- C14% (6)
- D7% (3)
Community Discussion
No community discussion yet for this question.