A Business Process (BP) has been identified that failed due to an issue with the Lightweight JDBC adapter using a database that is unavailable. The database has been made available again. The BP has…

The correct answer is B. Resume. See the full explanation below for the reasoning.

Question

A Business Process (BP) has been identified that failed due to an issue with the Lightweight JDBC adapter using a database that is unavailable. The database has been made available again. The BP has no built in OnFault logic. To reprocess the failed BP, which action to be executed is the most efficient for each of the failed instances?

Options

  • ARestart
  • BResume
  • CAdvanced Restart
  • DTerminate and Resubmit

How the community answered

(55 responses)
  • A
    5% (3)
  • B
    78% (43)
  • C
    13% (7)
  • D
    4% (2)