IBM
A2010-653 · Question #66
A2010-653 Question #66: Real Exam Question with Answer & Explanation
The correct answer is B. Synchronous workflow. See the full explanation below for the reasoning.
Question
What type of workflow can be called from an onChange event?
Options
- ASubflow workflow
- BSynchronous workflow
- CAsynchronous workflow
- DScheduled event workflow
Community Discussion
No community discussion yet for this question.