A packaged goods company is migrating its current site to AEM. The company has a presence in the US, but is expanding into two other countries within 12 months of launch on AEM. During which two…

The correct answer is B. Component development C. Workflow implementation. See the full explanation below for the reasoning.

Question

A packaged goods company is migrating its current site to AEM. The company has a presence in the US, but is expanding into two other countries within 12 months of launch on AEM. During which two tasks should the architect consider this expansion goal? (Choose two.)

Options

  • ASite hierarchy definition
  • BComponent development
  • CWorkflow implementation
  • DContent migration

How the community answered

(56 responses)
  • A
    11% (6)
  • B
    84% (47)
  • D
    5% (3)