Microsoft
98-364 · Question #59
Which of the following is undertaken at any time prior to the logical design, provided that sufficient information is available regarding system requirements?
The correct answer is C. DBMS selection. See the full explanation below for the reasoning.
Question
Which of the following is undertaken at any time prior to the logical design, provided that sufficient information is available regarding system requirements?
Options
- AApplication design
- BPrototyping
- CDBMS selection
- DDatabase planning
How the community answered
(53 responses)- A4% (2)
- B6% (3)
- C79% (42)
- D11% (6)
Community Discussion