Arrange the various activities of an application lifecycle in the order in which they are likely to occur.

The correct answer is A. Requirements analysis, design, coding, testing, and release. See the full explanation below for the reasoning.

Question

Arrange the various activities of an application lifecycle in the order in which they are likely to occur.

Options

  • ARequirements analysis, design, coding, testing, and release
  • BDesign, requirements analysis, coding, testing, and release
  • CRelease, requirements analysis, coding, testing, and design
  • DRequirements analysis, design, release, coding, and testing