Which two options are commonly used to help calculate the size of an identified risk? (Choose two.)

The correct answer is B. frequency of occurrence D. level of impact. See the full explanation below for the reasoning.

Question

Which two options are commonly used to help calculate the size of an identified risk? (Choose two.)

Options

  • Acomplexity of solution
  • Bfrequency of occurrence
  • Cnumber of dependencies
  • Dlevel of impact
  • Enumber of diagnostic steps

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    71% (20)
  • C
    4% (1)
  • E
    11% (3)